Critical Path Analysis

MS-N3 is worth about 6 marks out of 100 in recent HSC Mathematics Standard 2 papers. Practise 6 exam-style questions (multi-part, multiple choice) with instant marking and a worked solution for every question.

START PRACTISING

Example questions

Example 1 · 1 mark · multiple choice

An activity has a float time of 3 days. What does this mean?

  1. AIt takes 3 days to complete
  2. BIt must start exactly 3 days after the project begins
  3. CIt can be delayed by up to 3 days without delaying the whole project
  4. DIt is on the critical path

Example 2 · 1 mark · multiple choice

A project has these activities.

ActivityDuration (days)Immediate prerequisites
A5–
B3–
C4A
D7B
E2C, D

Which is the critical path?

  1. AB–D–E
  2. BA–C–E
  3. CA–B–C–D–E
  4. DB–D

Example 3 · 4 marks · multi-part

A project has the activities below.

ActivityDuration (days)Immediate prerequisites
A3–
B5–
C4A
D6A, B
E2C
F3D, E

Answers and worked solutions appear when you practise these questions.